Birmingham
Oxmoor Valley, AL, United States
Status
construction
Contracted
300 MW
Live
n/a MW
Build estimate
35%
Initial phase commissioning Q4 2026, full build through 2028. Zoning and permit validity under legal challenge, non-jury trial 8 Mar 2027.
Primary record: Oxmoor Valley project pageMilestones and evidence
First data center role in Birmingham
First posting observed in the tracked history.
Nebius public careers boardBirmingham recorded as construction
Initial phase commissioning Q4 2026, full build through 2028. Zoning and permit validity under legal challenge, non-jury trial 8 Mar 2027.
Oxmoor Valley project pageEnergization target
Target or inferenceA company or operator target, not completed capacity.
Oxmoor Valley project pageBirmingham (Oxmoor Valley) initial phase commissioning
Target or inferenceZoning and permit validity are under challenge, with a non-jury trial set for 8 March 2027. The later 2028 phases carry more of that exposure than this one.
Oxmoor Valley project pageAlabama zoning trial (Oxmoor Valley permits)
Non-jury trial on whether the permits complied with Birmingham's zoning ordinance. Courts rarely unwind completed construction, but the later phases are the exposure.
Court schedule reported in filings coverageHiring history
CSV- 1 Jan 20261 open data center role
First detection in the tracked history.