Birmingham

Oxmoor Valley, AL, United States

Status

construction

Contracted

300 MW

Live

n/a MW

Build estimate

35%

Initial phase commissioning Q4 2026, full build through 2028. Zoning and permit validity under legal challenge, non-jury trial 8 Mar 2027.

Primary record: Oxmoor Valley project page
Loading map

Milestones and evidence

9 Jan 2026

First data center role in Birmingham

First posting observed in the tracked history.

Nebius public careers board
30 Jun 2026

Birmingham recorded as construction

Initial phase commissioning Q4 2026, full build through 2028. Zoning and permit validity under legal challenge, non-jury trial 8 Mar 2027.

Oxmoor Valley project page
31 Dec 2026

Energization target

Target or inference

A company or operator target, not completed capacity.

Oxmoor Valley project page
31 Dec 2026

Birmingham (Oxmoor Valley) initial phase commissioning

Target or inference

Zoning and permit validity are under challenge, with a non-jury trial set for 8 March 2027. The later 2028 phases carry more of that exposure than this one.

Oxmoor Valley project page
8 Mar 2027

Alabama zoning trial (Oxmoor Valley permits)

Non-jury trial on whether the permits complied with Birmingham's zoning ordinance. Courts rarely unwind completed construction, but the later phases are the exposure.

Court schedule reported in filings coverage

Hiring history

CSV
  1. 1 Jan 20261 open data center role

    First detection in the tracked history.