Company targetUpdated 25 Aug 2026
Vineland NJ
Vineland, NJ, United States
Status
construction
Contracted
800 MW
Live
610 MW
Build estimate
76%
Capacity dedicated in large part to the Microsoft commitment. Operator-maintained estimate.
Primary record: Q2 2026 shareholder letterLoading map
Milestones and evidence
27 Jan 2026
First data center role in Vineland
First posting observed in the tracked history.
Nebius public careers board30 Jun 2026
Vineland NJ recorded as construction
Capacity dedicated in large part to the Microsoft commitment. Operator-maintained estimate.
Q2 2026 shareholder letter31 Dec 2026
Energization target
Target or inferenceA company or operator target, not completed capacity.
Q2 2026 shareholder letter31 Dec 2026
Vineland NJ full-capacity target
Target or inferenceCompany timelines are targets, not commitments.
Q2 2026 shareholder letterHiring history
CSV- 1 Jan 20261 open data center role
First detection in the tracked history.
- 1 Feb 20262 open data center roles
- 1 Mar 20264 open data center roles
- 1 Apr 20266 open data center roles
- 1 May 20265 open data center roles
- 1 Jun 20267 open data center roles
- 1 Jul 20266 open data center roles
- 1 Aug 20261 open data center role