Vineland NJ

Vineland, NJ, United States

Status

construction

Contracted

800 MW

Live

610 MW

Build estimate

76%

Capacity dedicated in large part to the Microsoft commitment. Operator-maintained estimate.

Primary record: Q2 2026 shareholder letter
Loading map

Milestones and evidence

27 Jan 2026

First data center role in Vineland

First posting observed in the tracked history.

Nebius public careers board
30 Jun 2026

Vineland NJ recorded as construction

Capacity dedicated in large part to the Microsoft commitment. Operator-maintained estimate.

Q2 2026 shareholder letter
31 Dec 2026

Energization target

Target or inference

A company or operator target, not completed capacity.

Q2 2026 shareholder letter
31 Dec 2026

Vineland NJ full-capacity target

Target or inference

Company timelines are targets, not commitments.

Q2 2026 shareholder letter

Hiring history

CSV
  1. 1 Jan 20261 open data center role

    First detection in the tracked history.

  2. 1 Feb 20262 open data center roles
  3. 1 Mar 20264 open data center roles
  4. 1 Apr 20266 open data center roles
  5. 1 May 20265 open data center roles
  6. 1 Jun 20267 open data center roles
  7. 1 Jul 20266 open data center roles
  8. 1 Aug 20261 open data center role